Peterborough – Lidl RDC

Principle Contractor

TSL Projects

Key Stats

Concrete Poured: 4,670 m3
Drainage Installed: Qmax linear drainage 1,840 m
Kerbs & Edging: 4,000 m
Steel Reinforcement: 52 t mesh & loose bar

Project Information

Hennigan Building & Civil Engineering Ltd won the majority of the groundworks package for a new Lidl Distribution Warehouse in Peterborough for TSL. Our works included, foundations, dock leveller slabs, Q-max linear drainage and external works. The works were let on a 2 phase basis that we are due to complete within the coming weeks which will result in the project being completed within our clients target programme.