Ipswich – Port One Unit Six

Principle Contractor

Team AB Services Ltd

Key Stats

Foundations: 1,775 m³

Drainage Installed: 800 m

Kerbs & Edgings: 750 m

STEEL REINFORCEMENT
Mesh B785: 1,200 m²
Mesh B1131: 1,200 m²

ROADS & FOOTPATHS
Pedestrian Footpath: 1,750 m²
Car Park: 1,735 m²
Service Yard: 2,200 m²

Service Ducting: 300 m

Landscaping: 250 m³

Project Information

We were awarded the groundworks package by Team AB Services Ltd in March 2022. The scope of works consists of completing the main building pad foundations, main foul & storm drainage, office drainage connections, external finishes, utilities ducting, stoning up all external areas to underside of finished surface & topsoil spread to landscaped areas.

We are currently tendering buildings 7-10 for Team AB Services Ltd on the same site which is due to start in July 2022.