Fenny Lock – Project Usher

Principle Contractor

Glencar Construction Ltd

Key Stats

Foundations: 1,650 m³

DRAINAGE INSTALLED
Main Below Ground Drainage: 2,000 m²
Linear Drainage: 455 m²

External Yard Slabs: 8,550 

Steel Reinforcement: 12,465 m²

ROADS & FOOTPATHS
Pedestrian Footpath: 1,255 m²
Car Park: 4,890 m²
Service Yard: 8,550 m²

Service Ducting: 1,800 m

Landscaping: 250 m³

Project Information

We completed the groundworks package for Glencar Construction in April 2022. The scope of works consisted of completing the main building pad foundations for 2nr units, main foul & storm drainage, linear drainage & office drainage connections, external finishes, external concrete yard slabs, utilities ducting, stoning up all external areas to underside of finished surface & topsoil spread to landscaped areas.